On a custom machine, most of the purchasing work starts with RFQs: you have a BOM, and you need prices and lead times before you can order. Doing this from a spreadsheet works for a few lines. On a machine with a few hundred lines, it is where dates and prices get lost.

1. Start from a flat, current BOM

Purchasing needs each part once, with its total quantity for the machine. Export a "Parts only" or flat BOM from your CAD system and check the revision before you send anything. If engineering changes the BOM later, you want to know which RFQs it affects.

2. Check stock first

Before you ask suppliers for a price, check what you already have. Parts in stock do not need an RFQ, and parts shared with other jobs should not be counted twice.

3. Group lines by supplier and purchase type

Group catalog parts by distributor, machined and fabricated parts by shop, and long-lead items separately. Long-lead items should go out first, because their dates drive your FAT date.

4. Send each supplier what it needs to quote in one pass

  • part number and revision, description and quantity
  • drawing or model for made-to-print parts, with material and finish
  • required delivery date (a date, not "ASAP")
  • documents you need with the parts: delivery note, certificate of conformity, material certificate

5. Keep the answers with the parts list

When quotes come back, the price and promised date belong on the part's line, not in an email. Then the purchase order can be made from the same line, and a late promise date is visible against the build schedule.

6. Order, then track each line

After ordering, track each PO line until the full quantity is in. Example: 40 ordered, 28 arrived, 12 outstanding. The line is not done until all 40 are received.

Doing this in AssembleFlow

  • import the BOM from Excel or your CAD export
  • send RFQs and purchase orders straight from the parts list, after checking stock
  • see what a late part does to your FAT and SAT dates
  • record partial deliveries against each PO line, with received and outstanding quantities

Limits, honestly: inquiry and purchase order lines are made per parts list row. If the same part number is on several rows, it appears on several lines and is not merged; import a flat BOM to avoid that.

Try it on one of your own machines: start a 14-day free trial (no card), or apply for the free 3-month pilot on one real machine build.

Ready to leave Excel behind?

Start your free 14-day AssembleFlow trial — no credit card required.

Start free trial