For converting machine builders

BOM and purchasing for converting and web-handling machine builders

A converting line is built from a long list of bought-in parts: drives and motors, bearings and rollers, air shafts and chucks, tension sensors, guides, pneumatics and controls, next to the frames and parts you make yourself. Each line is a little different, the build takes weeks or months, and the customer expects a spare parts list at the end. AssembleFlow keeps the parts list, purchasing and deliveries for each machine in one shared project.

What makes these builds hard to track

  • Long-lead parts. Drives, gearboxes and special rollers can take many weeks, and one late item can hold up assembly and the FAT date.
  • Parts mixed between builds. When two lines are on the floor, it is easy to take a part meant for one machine and use it on the other.
  • Deliveries in several lots. Rollers and machined parts often arrive in partial lots, and someone has to know how many are still outstanding.
  • Spare parts packages. Customers ask for a priced spare parts list, and building it by hand from the BOM takes time.
  • Job cost. On a long build, the true cost against the quote is often clear only at the end.

More on this: late parts tracking for custom machine builders and job costing for special-purpose machines.

How AssembleFlow helps

Each machine gets one shared project where you can:

  • import the BOM from Excel or your CAD export
  • keep one parts list per machine, with shared stock across all jobs
  • send RFQs and purchase orders straight from the parts list, after checking stock
  • see what a late part does to your FAT and SAT dates
  • record partial deliveries against each PO line, with received and outstanding quantities
  • track job cost against budget and turn it into a customer quote
  • produce a priced spare parts list and a parts manual for each customer

For example, if 40 rollers were ordered and 28 have arrived, the PO line shows 12 outstanding until the last lot is received.

Want to start in Excel? The free templates include a spare parts list template.

Honest limits

AssembleFlow imports BOMs as spreadsheets (CSV, XLSX, XLSM, XLS) and cannot open native CAD files. It does not roll up quantities through subassemblies or merge identical part numbers into one PO line, so import a "Parts only" (flat) BOM to get one line per part with its total quantity. There is no per-part price history across orders or projects.

Try it on one of your own machines

Send us the Excel BOM of one machine, an old or finished one is fine, and we will set it up for you. Or start the 14-day free trial, no card needed. See how the 3-month pilot works.

Other industries: Packaging machine builders, Test stand builders, Welding automation builders, Medical device automation builders, Food processing machine builders, Robotic cell builders, Material handling equipment builders, Inspection and vision machine builders, Press and forming equipment builders, Assembly automation builders.

Frequently asked questions

Can stock be shared between two machines on the floor?

Yes. Stock is shared across all jobs. When one stock item matches several rows, Apply Stock shares the available quantity between them.

Can I make a spare parts list for the customer?

Yes. Each project can produce a priced spare parts list and a parts manual.

Can a PO line be received in several lots?

Yes. Each receipt records a quantity, a date and a note, and the line shows ordered, received and outstanding.

How do I try it?

Start the 14-day free trial without a card, or, if you are a small machine builder, request the free 3-month pilot on one real build.

Request the 3-month pilot Start the 14-day trial