Most late machines are not late because of design. They are late because one bought-in part was not ordered in time, arrived short, or arrived damaged and nobody noticed until assembly. This checklist is the one I use as a mechanical design engineer. Use it per machine.
Before you order
- The BOM is final enough to buy from. Parts, quantities and revision are agreed between design and purchasing. If your CAD system offers a flat "Parts only" BOM type, export that: it lists each part once with its total quantity.
- Quantities are totals, not per subassembly. If a subassembly is used four times and holds six screws, you need 24, not 6. Add them up before you buy. Example: 5 screws x 8 assemblies = 40. More on this: how to total subassembly quantities in a multi-level BOM.
- Stock is checked first. Take what is on the shelf before you create an order.
- Every line has a supplier. Lines without one are the ones that get forgotten.
- MOQs are checked. A minimum order quantity can mean buying 100 when you need 40; decide whether that is fine.
- Long lead time parts are ordered first. Sort by lead time, not by assembly. See long lead time parts: how machine builders order early.
- Delivery dates are compared with the FAT date. If a part arrives after the date you need it, say so now, not at assembly.
After you order
- One order per supplier, with a number and a date. Easy to quote when the supplier calls.
- The supplier confirms the order and the delivery date. An order without a confirmation is only a request.
- Goods are booked in against the order line. Record what arrived and what is still outstanding, for example 40 ordered, 28 arrived, 12 outstanding. Do not tick the whole order as received when only part of it came.
- Problems are written down when found. Shortage, wrong item, damaged or rejected, with the number of pieces. Mark them settled when the replacement or credit arrives. More on this: how to track partial deliveries and damaged parts without an ERP.
- Delivery notes and certificates are filed with the line. Material certificates, certificates of conformity and inspection reports belong with the part they cover, not in a shared folder.
Not sure what a term means? See the machine building glossary. Prefer a spreadsheet? The free Excel templates include a purchase order tracker.
FAT coming up? Run the parts readiness check before a factory acceptance test two to three weeks before the date.
Doing this in AssembleFlow
AssembleFlow keeps one parts list per machine. You can import the BOM from Excel or your CAD export, send RFQs and purchase orders straight from the parts list after checking stock, see what a late part does to your FAT and SAT dates, record partial deliveries against each PO line with received and outstanding quantities, log shortages, wrong, damaged or rejected parts, and attach delivery notes and certificates.
AssembleFlow does not add up repeated subassembly quantities for you, and it does not merge identical part numbers into one order line, so use the Parts only export in step 2. More straight answers are in the purchasing FAQ.
Try it free for 14 days with no card, or request the free 3-month pilot on one real machine build.